JSA successfully represented Essar Power Transmission Company Limited in overturning CERC’s disallowances on capital costs and delays for its Gandhar – Hazira inter-State Transmission Line. On...
Essar Power Transmission Company Limited’s Disallowances on Capital Costs and Delays
Mundra Ultra Mega Power Plant’s Securing a Change in Law compensation for Impact on Capital
JSA successfully represented Tata Power’s Mundra Ultra Mega Power Plant on the case. On 25.10.2024, the Appellate Tribunal for Electricity (APTEL) delivered a significant judgment partly...
Sundew Properties’ Dispute before Supreme Court
JSA represented Sundew Properties Limited on the deal. In a landmark judgment on May 17, 2024, the Supreme Court clarified the relationship between the SEZ Act,...
Maharashtra Border Check Post Network Limited’s Petition before MERC
JSA successfully represented Maharashtra Border Check Post Network Limited on the deal. Maharashtra Border Check Post Network Limited partecipated in a petition before Maharashtra Electricity Regulatory Commission,...